Rehabilitation of the Import Berth Platform (IBP) and Tank Farm Facilities

Project     Rehabilitation of the Import Berth Platform (IBP) and Tank Farm Facilities
Client    Pipeline and Product Marketing Company Limited (PPMC)
Country    Nigeria
Project-Period    2002 - 2003

Purpose:

Rehabilitation of the Crude Oil Import System at Escravos.

Technical data:

Import system comprising of:

  • Floating hose with “Y“ tank
  • Single Bouy Morring (SBM)
  • Single submarine hose and PLEM
  • 30“x2.2km sub sea pipeline from PLEM to IBP
  • Four pile jacket with cellar and main deck
  • 26“x28km sub sea pipeline from IBP to Escravos Tank farm
  • 5x63,370 m3 float-roof storage tanks at Escravos Tank Farm with Pumping and Power Generation facilities.

ILF Services:

  • Collection and review of as-built works and drawings
  • Establish technical feasibility of the Rehabilitation Concept by carrying out hydraulic calculations
  • Inspection of the facilities
  • Prepare Rehabilitation Concept, Basic Engineering and the scope of works to be performed by Contractor
  • Assist PPMC in adjudicating the Contract price
  • Project Management
  • Vet Detailed Engineering documents
  • Construction supervision
  • Supervision of commissioning activities.